365 days since the Commencement Order of the 1st lot of the Rato-Cais Sodré Extension and Campo Grande Viaducts.
14 April 2022 marks one year since the consignment of the Design – Build Contract for the Extension of the Rato- Santos Yellow Line – Lot 1 of the Lisbon Metro Circular Line.
The project includes 1984 m of double-track tunnel, 2 new stations – Estrela and Santos, 2 new ventilation wells and a new atrium at the Cais Sodré station.
The lines connection to the north, in Campo Grande, is also planned, with the creation of 2 new sections between the existing viaducts, which will allow the ring connection of the Green Line, coming from Alvalade, with the ‘Cidade Universitária’ section, from the Yellow Line and also the connection between the stations of Telheiras and Quinta das Conchas.
These works have a total expected duration of 4 years, with completion in the 2nd half of 2024.
The Group awarded the Coordination and Supervision contract has currently mobilized a multidisciplinary team of 33 technicians, being responsible for the activities of Administrative Management, Works Planning and Execution Control, Verification, Costs and Quantities Control, Quality System Management, Environmental System Management, Health and Safety on site and also Risk Management, Interfaces and RAMS Supervision.
The scope of the intervention encompasses 4 different contracts that include Roughwork, Finishes, Track, Signaling, Mechanical Access, Ventilation and Fumes Removal, Pumping, Medium-Voltage and Low-Voltage, SCIE.